Streets Ahead improvements are finally due for completion in Tapton Hill
The remaining work on replacing street lights and resurfacing pavements in the Tapton Hill area is finally due to for completion at the end of June/early July, contractor Amey has announced.
Meanwhile, preparation work has started on some streets in and around Sandygate as the Streets Ahead project moves onto the next area of our neighbourhood, with weeds and grass being cleared along curbstones.
You’ll have the chance to find out more in Crosspool next week about Streets Ahead, the project to renew the roads, pavements and streetlights of Sheffield.
The Streets Ahead roadshow arrives in Crosspool at The Sportsman pub on Tuesday 13 May from 2-4pm and will then move on to The Florentine 5-7pm.
Resurfacing work is already underway in areas of Tapton Hill and work around Crosspool is scheduled to continue throughout 2014.
This online map allows you to search by postcode to find an approximate date for when the work will take place on your street.
Roadworks in Broomhill caused major delays this morning
Roadworks and temporary traffic lights have caused major bottlenecks through Broomhill this morning.
Emergency work by Northern Powergrid is taking place to repair a cable fault outside On-A-Roll sandwich shop causing power loss to local businesses. Only one lane of traffic is able to pass through at a time.
Earlier today, the 51 bus was diverted in both directions, bypassing Weston Park and the university stops.
The map on roadworks.org shows progress with the repair, although there is no firm indication yet how long it will take.
Update 2pm: reports that Broomhill is now clear of the works and there are no longer any major hold ups.
The A57 at Crosspool reopened on Monday lunchtime to single lane traffic after three weeks of maintenance work.
The road was closed in both directions from Hagg Lane and Coldwell Lane to the junction of Rivelin Valley Road at the beginning of November. The closure was to allow major repairs to be carried out following a landslip.
Andrew Harley, Construction Manager at Amey who are carrying out the work as part of the Streets Ahead project, said: “We’ve dug deep under the road to replace a damaged drain and to dig out more than 700 tonnes of clay and rock and install supports to help prevent further land movement.
“We are now ready to make further repairs on the upper embankment and plan to have the rest of the work finished and the road fully reopened by the end of January.”
The Bamford bus is also now running as normal once again.
Manchester Road will close for three weeks in November to allow for the repair of a collapsed drain under the road.
From 11pm on Friday 8 November 8 to 6am on Monday 2 December 2013 the road will be closed as follows:
Outbound after Hagg Lane and Coldwell Lane (with notices that access will be maintained for the local businesses and residents)
Inbound at the junction of the A57/A6101 Rivelin Valley Road. Local traffic will be able to access Lodge Lane via Rails Road but HGVs will be diverted via Malin Bridge
The A57 will then reopen again to single lane traffic while further work is carried out to stabilise the slope below the road. Once this is completed, the road will fully reopen at the end of January 2014. Pedestrian access will be maintained while this work is carried out.
Contractors Amey will advantage of the road closure to carry out other works at the same time including pruning of trees, clearing overgrown footpaths, some footpath repairs and clearing drainage gullies.
Sign warning motorists of A57 Manchester Road repairs
Streets Ahead improvements have been delayed in Tapton Hill
Crosspool residents living on Tapton Hill are receiving notifications from Streets Ahead notifying them of delays to the improvements and new dates for when work will take place.
On Monday 5 August, work commenced a month later than planned on Vernon Terrace, Ryegate Road, Ryegate Crescent and Bosville Road. People living on these streets should have received a letter about this.
Lydgate Lane residents were expecting work to begin at night on 12 and 15 August, but this has been delayed and will instead take place Monday 19 to Friday 23 August 2013 between 7am and 7pm. Cars will be diverted, although access for pedestrians and emergency vehicles will be available at all times.
After a review of road conditions in the area, Cross Lane will now also be resurfaced. Residents will be informed by letter once a date is confirmed.
Underground cabling issues have meant that installation of new street lighting in Tapton Hill will start in November with a projected completion date of January. The heritage lights which are due to be installed in the Broomhill conservation area are on order. Pavements will be resurfaced as street lights are replaced.
Telecommunications work by BT is causing delays for motorists on Manchester Road near the Shore Lane junction, where two-way temporary traffic lights have been installed.
The work started this weekend and is expected to go on until Tuesday 18 June – although sometimes planned maintenance like this can take less time than estimated.
Any queries should be addressed to BT quoting reference BC005WP00100500109785506.
During Crosspool Forum’s April Open Meeting, it was reported that the temporary traffic signals and roadworks on the A57 Manchester Road are one year old this May.
The work is the result of a serious subsidence problem which has spread significantly since it was first identified and is now affecting the retaining wall.
Although it may appear to regular users of the road that little has been done other than the siting of temporary signals, Amey has been monitoring the subsidence and has drilled several boreholes as part of its investigations. It appears that the problem is more complex than originally believed, meaning further surveys have been required.
Two options have been identified to stabilise the ground and stop further subsidence. The first involves driving concrete pilings, twelve metres in length, into the ground to support the embankment.
The second, reported recently in the Sheffield Star, uses electricity. The method involves inserting electrodes into the ground: the electrical current stabilises the ground beneath by altering the properties of the rock and soil. This method has been used successfully in similar situations and may be an option for the A57.
Our councillors and Amey inform us that the work is due to start in May or June so we may have seen the last of the chicane by the end of summer.