The A57 at Crosspool reopened on Monday lunchtime to single lane traffic after three weeks of maintenance work.
The road was closed in both directions from Hagg Lane and Coldwell Lane to the junction of Rivelin Valley Road at the beginning of November. The closure was to allow major repairs to be carried out following a landslip.
Andrew Harley, Construction Manager at Amey who are carrying out the work as part of the Streets Ahead project, said: “We’ve dug deep under the road to replace a damaged drain and to dig out more than 700 tonnes of clay and rock and install supports to help prevent further land movement.
“We are now ready to make further repairs on the upper embankment and plan to have the rest of the work finished and the road fully reopened by the end of January.”
The Bamford bus is also now running as normal once again.
Manchester Road will close for three weeks in November to allow for the repair of a collapsed drain under the road.
From 11pm on Friday 8 November 8 to 6am on Monday 2 December 2013 the road will be closed as follows:
Outbound after Hagg Lane and Coldwell Lane (with notices that access will be maintained for the local businesses and residents)
Inbound at the junction of the A57/A6101 Rivelin Valley Road. Local traffic will be able to access Lodge Lane via Rails Road but HGVs will be diverted via Malin Bridge
The A57 will then reopen again to single lane traffic while further work is carried out to stabilise the slope below the road. Once this is completed, the road will fully reopen at the end of January 2014. Pedestrian access will be maintained while this work is carried out.
Contractors Amey will advantage of the road closure to carry out other works at the same time including pruning of trees, clearing overgrown footpaths, some footpath repairs and clearing drainage gullies.
Sign warning motorists of A57 Manchester Road repairs
Streets Ahead improvements have been delayed in Tapton Hill
Crosspool residents living on Tapton Hill are receiving notifications from Streets Ahead notifying them of delays to the improvements and new dates for when work will take place.
On Monday 5 August, work commenced a month later than planned on Vernon Terrace, Ryegate Road, Ryegate Crescent and Bosville Road. People living on these streets should have received a letter about this.
Lydgate Lane residents were expecting work to begin at night on 12 and 15 August, but this has been delayed and will instead take place Monday 19 to Friday 23 August 2013 between 7am and 7pm. Cars will be diverted, although access for pedestrians and emergency vehicles will be available at all times.
After a review of road conditions in the area, Cross Lane will now also be resurfaced. Residents will be informed by letter once a date is confirmed.
Underground cabling issues have meant that installation of new street lighting in Tapton Hill will start in November with a projected completion date of January. The heritage lights which are due to be installed in the Broomhill conservation area are on order. Pavements will be resurfaced as street lights are replaced.
Telecommunications work by BT is causing delays for motorists on Manchester Road near the Shore Lane junction, where two-way temporary traffic lights have been installed.
The work started this weekend and is expected to go on until Tuesday 18 June – although sometimes planned maintenance like this can take less time than estimated.
Any queries should be addressed to BT quoting reference BC005WP00100500109785506.
Residents living in the vicinity of Tapton Hill Road and Tapton Bank have expressed their concerns about the recent increase in vehicles parking outside their properties, adding further congestion at school times.
Sheffield West Delivery Office has taken delivery of 26 new vehicles which now occupy their onsite car park, meaning the vehicles which previously parked there are now parking in the surrounding streets.
One resident has contacted the site manager to raise her concerns and other residents brought up the matter with local councillors at a recent Crosspool Forum open meeting.
Members of the Forum also met with management at the delivery office on Wednesday 1 May and the Post Office will be carrying out a feasibility study to look at options available to try and improve the onsite parking within the site.
During Crosspool Forum’s April Open Meeting, it was reported that the temporary traffic signals and roadworks on the A57 Manchester Road are one year old this May.
The work is the result of a serious subsidence problem which has spread significantly since it was first identified and is now affecting the retaining wall.
Although it may appear to regular users of the road that little has been done other than the siting of temporary signals, Amey has been monitoring the subsidence and has drilled several boreholes as part of its investigations. It appears that the problem is more complex than originally believed, meaning further surveys have been required.
Two options have been identified to stabilise the ground and stop further subsidence. The first involves driving concrete pilings, twelve metres in length, into the ground to support the embankment.
The second, reported recently in the Sheffield Star, uses electricity. The method involves inserting electrodes into the ground: the electrical current stabilises the ground beneath by altering the properties of the rock and soil. This method has been used successfully in similar situations and may be an option for the A57.
Our councillors and Amey inform us that the work is due to start in May or June so we may have seen the last of the chicane by the end of summer.
Our local councillors have met with First and SYPTE to discuss the 51 bus
Our three councillors, Sylvia Anginotti, Rob Frost and Geoff Smith, have recently met with First and South Yorkshire Passenger Transport Executive (SYPTE) to discuss the 51 bus route.
A report from the meeting, written by the councillors, is below.
The three Crookes councillors (Sylvia Anginotti, Rob Frost and Geoff Smith) have been made aware by individuals and through the Crosspool Forum of dissatisfaction with the 51 bus. In particular with the failure of buses to run at the published times.
We were going to have a meeting with First and South Yorkshire Passenger Transport Executive (SYPTE) in January but unfortunately the bad weather forced a postponement and we were not able to meet until March.
You will remember that we were promised an improved service when the Bus Partnership arrangements started at the end of October 2012. This was going to be achieved in two ways; an additional bus on the route and a change of route to avoid Broad Lane.
The additional bus was put on but the change of route didn’t happen. This was because of the number of people who protested that they would not be able to get to the NHS walk in service.
SYPTE figures for complaints show a continued high level of complaints up to January of this year and then a falling off. This could be for either of two reasons; people have become fed up with complaining or there has been some improvement in the service.
SYPTE’s own figures for punctuality at stops on the route show an improvement from 72% punctuality pre-October 2012 rising to 84% recently. This is against a target of 95%. So even by their own figures there is still some way to go.
First admit that punctuality is still not good enough. They said that double deckers were part of the problem and that from early July they will be replaced by brand new single deckers which along with ticket issue speeding up should speed up overall loading times.
They are also putting an additional bus on the route on Saturdays from the end of April and making minor timetable changes. They gave us a list of traffic hotspots on the route which cause problems and we will be taking these up with the Council.
Also they warned that the service could be affected by planned roadworks across the city.
We will continue to have meetings with First and SYPTE. We will welcome your views and experience at the next meeting of the Crosspool Forum and please keep on complaining to SYPTE if you have problems with the 51.
Sylvia Anginotti, Rob Frost and Geoff Smith
April 2013
The temporary traffic lights in Broomhill are not due to be removed until Monday 4 March.
Work is currently underway to excavate up to 15 meters of footway to locate high voltage cables that have caused loss of power.
The multi-way temporary traffic lights are causing delays to traffic travelling through Broomhill. During the morning rush hour tailbacks are stretching up Manchester Road all the way to Crosspool, causing delays to commuters.
Update 28 February: the wors appear to have been completed unexpectedly early, so the temporary traffic lights have now been removed.
Drivers on the bottom end of Manchester Road will have noticed the electronic speed indication displays (SIDs) return last month. We got in touch the council to find out what data about traffic speeds the SIDs have collected.
The speed limit for this stretch of road is 30mph. The idea is that the SIDs slow cars down by making drivers aware when they are driving at unsafe speeds.
The data below from previous periods when SIDs have been installed on Manchester Road shows a reduction in average speed when they are present:
Period
Average vehicle speed into town
Average vehicle speed away from town
No SIDs on site
34mph
31mph
February 2011
31mph
29mph
July 2010
31mph
27mph
The SIDs on Manchester Road will be there for an eight-week period before they are rotated to another site by the Central Community Assembly.