Thirty one trees along Rivelin Valley Road could be removed as part of the Streets Ahead road improvement project.
According to the Sheffield Telegraph, contractor Amey says three trees are either dead, decayed, have structural integrity problems or are causing surface damage.
Residents are campaigning against the proposals.
A Streets Ahead roadshow is due to visit Stephen Hill church on Tuesday 24 November, 4-7pm.
The 51 bus route will be changed slightly due to resurfacing works for the next three Sundays.
On Sundays 22 and 29 November and 6 December from 6am to 5pm the Crosspool-bound 51 bus will travel as normal to to Western Bank then go left down Clarkson Street, right onto Glossop Road, left to Fulwood Road then continue as normal to Lodge Moor.
Work as part of Streets Ahead to upgrade Manchester Road will start towards the end of November.
The streetlights will be replaced as part of the first phase of the project, with the installation process taking up to six weeks. The Manchester Road trees will also be assessed and possibly replaced.
You can find out more about the planned work at an upcoming roadshow which will be visiting Stephen Hill church on Tuesday 24 November, 4-7pm.
200-year-old trees on Lydgate Lane are scheduled to be cut down as part of the Streets Ahead project.
Notices have been placed by Amey/Streets Ahead on three trees stating they have developed a structural fault and are to be felled within two weeks – possibly on Wednesday 28 October – as part of the city-wide programme to improve Sheffield’s roads.Â
Campaigners have organised an emergency meeting at 5pm Sunday 25 October in The Sportsman pub on Benty Lane – anyone with an interest in the fate of these trees is invited. Dave Dillner from Sheffield Tree Action Group will be attending. A petition to save the trees is also available for signing in Enhance Hair Salon.
Anyone wanting to express their views on the proposals to representatives from Amey and local councillors will also have the opportunity to do so at the next Crosspool Forum Open Meeting/AGM on 29 October at St Columba’s Church, 7pm start.
Concerned Crosspool residents are collecting signatures for a petition regarding the position of the painted white lines on Sandygate Road.
The road markings were repainted following resurfacing work and have divided the road into a wider uphill lane and a narrower downhill lane.
Resident Marie Biggs explained: “My main concern is that vehicles are travelling far too fast up the road and hogging the white lines. This doesn’t leave any space for vehicles and cyclists travelling downhill towards Crosspool, which have to cross the white lines to pass parked vehicles.
“Amey/Streets Ahead told me that the reason the lines are as they are is to allow for the safe overtaking of cyclists coming uphill – but what ablout the cyclists travelling downhill?
“And, if there was to be a collision, would drivers travelling down the road always be deemed to be at fault, purely because they are straddling the white lines?”
The petition can be signed in GT News and the Post Office.
What do you think of the position of the Sandygate Road markings?
Update 3 August: After all the fuss, it seems the 51 is going via Manchester Road/Coldwell Lane after all.
31 July, 9am update: First Bus have announced that they will provide a free shuttle bus between Crosspool and Brook Hill. This will operate every 30 minutes between approximately 7.30am and 6.30pm. No fares will be charged – this is to feed into the main 51 bus.
The 51 bus service will not run along part of Sandygate Road next week during the day due to road improvement works for the Streets Ahead project.
From Monday 3 to Friday 7 August, from 7am-7pm each day, 51 buses will run between Broomhill and Sandygate along Fulwood Road, Gladstone Road, Ivy Park Road, Carsick Hill Road and re-join the normal route on Sandygate Road to and form Lodge Moor.
Buses on services 273, 274 and 275 are not affected and will still run along Manchester Road and along Benty Lane and Sandygate Road travelling towards the city centre through Crosspool as normal.
At the Crosspool Forum Open Meeting last night concerns were raised in particular about families not being able to easily access Ryegate Children’s Centre on Manchester Road.
Cairns Road: trees will be removed for the delayed resurfacing project
The resurfacing of Cairns Road for the Streets Ahead project has been delayed until the end of September so that some of the road’s trees can be removed.
It was due to take place the week commencing 14 July but inspections have revealed that a number of trees need to be removed because they are causing damage to the road.
This work has been rescheduled for the week commencing 29 September. Residents will be written to nearer the time to confirm dates.
Amey have confirmed that any trees removed from Cairns Road will be replaced.
The trustees of Crosspool & District Youth Sports Trust are asking people to stop parking in their Coldwell Lane car park unless you are genuinely using the CDYST facilities or already have an arrangement to park there – for example Claremont Hospital.
Some residents have been using the private CDYST car park during road resurfacing works, which has been causing problems for existing users.
The trustees have warned that it is extremely dangerous for the mothers and pre-school children to have to park on a public road to get to the hall.
Streets Ahead improvements are finally due for completion in Tapton Hill
The remaining work on replacing street lights and resurfacing pavements in the Tapton Hill area is finally due to for completion at the end of June/early July, contractor Amey has announced.
Meanwhile, preparation work has started on some streets in and around Sandygate as the Streets Ahead project moves onto the next area of our neighbourhood, with weeds and grass being cleared along curbstones.
You’ll have the chance to find out more in Crosspool next week about Streets Ahead, the project to renew the roads, pavements and streetlights of Sheffield.
The Streets Ahead roadshow arrives in Crosspool at The Sportsman pub on Tuesday 13 May from 2-4pm and will then move on to The Florentine 5-7pm.
Resurfacing work is already underway in areas of Tapton Hill and work around Crosspool is scheduled to continue throughout 2014.
This online map allows you to search by postcode to find an approximate date for when the work will take place on your street.