Wet weather delays reopening of A57 Manchester Road

Temporary traffic signals on Manchester Road
Temporary traffic signals on Manchester Road

Manchester Road will fully reopen on Monday 3 March, four weeks later than originally planned.

Contractors Amey installed a new drain and gabions but wet weather has delayed the completion of the ground anchoring to the upper slope.

This means the single lane closure and temporary traffic lights will now be in place until March.

Temporary lights installed for roadworks on Manchester Road

Delays for motorists on Manchester Road
Delays for motorists on Manchester Road

Telecommunications work by BT is causing delays for motorists on Manchester Road near the Shore Lane junction, where two-way temporary traffic lights have been installed.

The work started this weekend and is expected to go on until Tuesday 18 June – although sometimes planned maintenance like this can take less time than estimated.

Any queries should be addressed to BT quoting reference BC005WP00100500109785506.

Delays for motorists on Manchester Road
Delays for motorists on Manchester Road

Broomhill roadworks to last until 4 March

The temporary traffic lights in Broomhill are not due to be removed until Monday 4 March.

Work is currently underway to excavate up to 15 meters of footway to locate high voltage cables that have caused loss of power.

The multi-way temporary traffic lights are causing delays to traffic travelling through Broomhill. During the morning rush hour tailbacks are stretching up Manchester Road all the way to Crosspool, causing delays to commuters.

Update 28 February: the wors appear to have been completed unexpectedly early, so the temporary traffic lights have now been removed.